Mr. Kumar is getting his house renovated. 1/5 th of the work has been completed in 2 months. How much time will it take for the entire work to be completed?

Respuesta :

liam2747
liam2747 liam2747
  • 02-05-2021

Answer:

10 months

Step-by-step explanation:

If it takes 2 months to do 1/5th, it will take 4 months to do 2/5, 6 months to do 3/5, 8 months to do 4/5, and 10 months to do 5/5 or in other words the whole thing.

Answer Link

Otras preguntas

Margarita is hired by an accounting firm at a salary of $60,000 per year. Three years later her annual salary has increased to $70,500. Assume her salary increa
what patterns are there in prime numbers
Is two thirds the same as four sixths
Which concept would states’ rights advocates have supported during the 1860 presidential election? the abolition of slavery the idea of popular sovereignty the
How does the number of atoms in one mole of argon compare with the number of molecules in one mole of ammonia
What is 10/25 simplified
How do I apply the change of base formula to y=log (sub 3) x
Does the following system have a unique solution? Why? 3x+2y= 9 14x + 10y = 14
Rene is going to the lake to visit some friends. If the lake is 60 miles away, and Rene is driving at 40 miles per hour the entire time, how long will it take h
What is the slope of the line if the rise of a line on a distance versus-time graph is 900 meters and the run is 3 minutes?