8 students take 18 hours to construct a raft.
If the raft needs to be completed 12 hours earlier, calculate how many more students are needed.

Respuesta :

devishri1977
devishri1977 devishri1977
  • 04-08-2021

Answer:

16

Step-by-step explanation:

Students                      8       x

Time taken (hours)     18     18 - 12 = 6

If number of students increases, the work will completed in less hours.

So inverse proportion

[tex]x =\frac{18*8}{6}=3*8 = 24[/tex]

Additional students required = 24 - 8 = 16

Answer Link

Otras preguntas

Which of the following statements best describes how most sociologists believe that gender differences in behaviour between men and women develop
Do you have answers for punnett square practice worksheet?
Helpp !! I Dont Understand This !
All of the following factors affect an area s biodiversity EXCEPT a. area. b. number of endangered species. c. climate. d. diversity of niches.
Which one of the following choices best represents an example of a positive social impact of a change in behavior? A. Peer pressure B. Attending functions that
What is the approximate volume of the sphere?
Affixes can provide an element of difference between similar words. Choose the correct word in the set below. You may use a dictionary for help. The telephone i
what can a chemical change be speeded up by?
The United States formally entered World War II following the Japanese attack on
How do I multiply and divide with exponents? See below for picture.